By Tricitynews Reporter
Chandigarh 06th
December:- The
water supply & sewerage disposal committee of MCC under the chairmanship of
Satish Kainth visited the site of Phase 5 & 6 water pipeline being executed
at Jandpur and sector 39, water works. The committee members were including Arun
Sood, Devinder Singh Babla, Vinod Aggarwal, Jagtar Singh, Ravi Kant Sharma, Sanjay
Arora, Superintending Engineer, Public Health wing and other concerned officers
of MCC.
They inspected the work of pipeline being laid from Jandpur to
Chandigarh. The officers informed the committee members that 90 percent of
length of pipeline has been laid. The members also asked the officers regarding
the completion of civil, mechanical and electrical works at Jandpur, and the
officers apprised that it will be completed by March, 2018.
During the
inspection of work at sector 39 water works, it was observed that about 50
percent of the work of water treatment plant has been completed and the
construction of clear water tank & storage/sedimentation tanks are about 30
percent completed. The machinery for the work has also been ordered and will be
received by January, 2018.
The officers
informed that the delay in work of Jandpur due to the late handing over of the
land by Punjab Govt. The councilors asked the officials to get the work
completed by April, 2018. Any matter with the Punjab Govt. regarding electrical
connection should be sorted out at the earliest to avoid any delay, the
committee assured.
Further, the
councilors were also appraised regarding the upgradation of water testing
laboratory at sector 39 water works under AMRUT which will include purchase of
new testing equipments and a mobile testing van for onsite testing of drinking
water.