10th February:- GOCL Corporation Ltd., a Hinduja
Group Company, has reported a consolidated turnover for Q-3 increase of 6.5% to
Rs. 134 crores ( Rs. 126 crores ) and an Operating Profit of Rs. 4.77
crores ( Rs. 3.17 crores). The Profit after Tax is Rs. 5.05
crores. The Standalone Turnover was Rs. 27 crores (Rs. 27 crores )
and Profit After Tax of Rs. 5.06 crores ( Rs. 5.58 crores ).
Overall sales of the Division during
the quarter have increased by 26% to Rs. 26 crores and the turnover for the
nine months period was Rs. 64 crores, an increase of 30%. The increase in
revenue during the third quarter was on account of improved domestic and export
sales of detonators, cartridged products and detonating fuse, registering an
all round growth.
IDL Explosives Limited (IDLEL), a
wholly owned subsidiary of the Company has achieved a turnover of Rs. 311
crores up to the third quarter ended December, 2016 an increase of 7%, and PBT
of Rs. 17 crores a substantial increase over the corresponding period of the
previous year.
The
Mining and Infrastructure Division achieved service income of Rs 6 crores as
against Rs. 17 crores in last year due to adverse market conditions
and regulatory environment in the metal mining sector.
Occupation Certificate for ‘Ecopolis’
Block 3 (10.46 lakhs sq.ft. ) + Multi Level Car Park space (4.06 lakhs sqft. )
has been obtained. Requirements for sale/lease/built-to-suit from clients
through International Property Consultants and through internal business
development initiatives are underway. Clients have completed site visits and we
have responded to RFP’s and RFI’s received. However in view of the fact that
the Residential developments and complementing Social Infrastructure nearer to ‘Ecopolis’ in
North Bengaluru are under development, some more time will be required for
finalizing the deals.
Construction of Block 2 comprising of
10.06 lakhs sq.ft. is underway. RCC works for 3 basements, ground floor and 10
upper floors has been completed. Contracts for purchase, installation and
commissioning of Mechanical, Electrical, Public Health, Fire Fighting, Facade works & Elevators are
currently being finalized and awarded.
Approvals for start of construction
of Block 1 comprising of 6.34 lakhs sq.ft. are being obtained. Construction
work will commence post approvals.